Bannock County Pavement Schedule

COLD MIX OVERLAY

Antelope, Crestview, Plainview

Timberline, Mountain Meadows, Promise Lane

Wallin, 2 1/2 miles (gun range to end), Fish Creek, Potter Approach

Baldy Mountain Road

 

 

HOT MIX OVERLAY

Jackson Creek Road

So. ​Dempsey Creek ​Road (city limits to Merrick Rd.)

 

*Subject to Change. May include all or portion of road & inclement in weather*

HILINE ROAD AND 2 1/2 MILE INTERSECTION

The re-construction of the Hiline Road and 2 1/2 mile intersection in 2013 took roughly 9 weeks (over 4300 labor hours total) and over $153,000 in hot mix alone to finish the 1 mile of road.  The redesign has 4 lanes which include turning lanes to increase safety.